3-1
• In this Section
• Check for Shorts to Ground
•Before Applying Power
• Applying Power
• Operating under Construction
• Verifying Starter Operation
• Install the Landing System
•Hoistway Limit Switches
• Door Position Monitor
• Complete Field Wiring
• Preparing to Run on Test
In this Section
This section discusses preparing the car to run on Inspection operation. It covers the sequence
of applying power to the controller and verifying proper motor rotation. It also covers complet-
ing the installation of hoistway equipment, initial adjustment of the system and preparing the
car for normal operation and final adjustment.
• Check for Shorts to Ground: How to check for shorts to ground (see page 3-2).
• Before Applying Power: Things to do before applying power (see page 3-2).
• Applying Power: Steps to apply power and check for proper pump motor rotation (see
page 3-3).
• Set Up for Construction Operation: Minimum requirements to allow the car to run
while still under construction (see page 3-4).
• Verifying Proper Starter Operation: How to verify proper starter operation (see
page 3-7).
• Installing the Landing System: Instructions for installing the landing system (see
page 3-9).
• Installing the Hoistway Limit Switches (LS-QUTE): How to install the hoistway
limit switches (see page 3-10).
• Door Position Monitor Switch: Installing the door position monitor switch, if used.
(see page 3-22).
• Complete the Installation and Field Wiring: Finish the installation and wiring and
check for shorts (see page 3-22).
• Preparing the Car to Run on Test/Normal Mode: How to prepare the car for run-
ning on automatic operation (see page 3-22).
Startup - Inspection Operation