Commissioning Proline Promass E 500 PROFIBUS PA
142 Endress+Hauser
If the adjustment was completed successfully, the Density adjustment factor parameter
and the Density adjustment offset parameter and the values calculated for them are
shown on the display.
"2 point adjustment" option
1. In the Density adjustment mode parameter, select the 2 point adjustment option
and confirm.
2. In the Density setpoint 1 parameter, enter the density value and confirm.
3. In the Density setpoint 2 parameter, enter the density value and confirm.
In the Execute density adjustment parameter the following options are now
available:
Ok
Measure density 1
Restore original
4. Select the Measure density 1 option and confirm.
In the Execute density adjustment parameter the following options are now
available:
Ok
Measure density 2
Restore original
5. Select the Measure density 2 option and confirm.
In the Execute density adjustment parameter the following options are now
available:
Ok
Calculate
Cancel
6. Select the Calculate option and confirm.
If the Density adjust failure option is displayed in the Execute density adjustment
parameter, call up the options and select the Cancel option. The density adjustment is
canceled and can be repeated.
If the adjustment was completed successfully, the Density adjustment factor parameter
and the Density adjustment offset parameter and the values calculated for them are
shown on the display.
Navigation
"Expert" menu → Sensor → Sensor adjustment → Density adjustment
Density adjustment
Density adjustment mode
→  143
Density setpoint 1
→  143
Density setpoint 2
→  143
Execute density adjustment
→  143
Progress
→  143