7-96 Section 7-5 - Monitoring Tests
7-5-1-3 Temperatures Test
NOTE: For a description of this test, refer to the information in Temperatures Test on page 7 - 14.
1.) In the Diagnostic Test window, trackball to Temperatures in the list of Monitoring tests available for 
selection from the Diagnostic Test Tree (see Figure 7-66 below) and press Set. The Temperatures 
Test name is displayed under Execute; all system components (excluding the P&M) will be tested 
are highlighted light blue in the Schematic View (all), as shown below:
2.) Under the Special Instructions area, activate the Loops checkbox 
and select the required number of Loops from the combo box.
3.) Adjacent to On Fail, select either Stop or Continue, as required. 
Stopping on failure enables you to review a failed test, the moment it fails. Alternatively, you may 
prefer testing to continue on failure and later you may review the report.
4.) Trackball to the Start button and press Set. 
The Temperatures Test commences. While the test proceeds, the name of the test currently in 
progress (Temperatures) is displayed in the Execute field and the current Loop # and specific test 
are shown below. The messages Init Done and Please Wait are displayed beside the progress bar 
in the Status area.
As the testing sequence progresses, the progress bar will advance to reflect the test progress. 
Status indicators in the Data Flow map corresponding to the various system components will be 
highlighted in the appropriate color to indicate the current test status, as follows:
• Green: All recommended tests for these components have been completed and no problems 
were identified.
• Red: Problems were identified in these components during the performance of the test.
NOTICE
IMPORTANT In order to access an individual board test, it is necessary to insert the service dongle from 
system boot-up and enter the Service Password.
Figure 7-66   Temperatures Test