Rack Installation - Assemble Controller Rack
62 HC900 Process Controller Installation and User Guide Revision 19
06/14
Step Procedure Comments/References
3
Ensure that AC power to
the rack is disconnected.
Set controller module’s
communication ports to
desired settings (page 36).
Carefully place the
Controller Module in the
rack, immediately to the
right of the Power Supply.
Fasten it in place with two
captured screws at top
and bottom.
ATTENTION:
Do not install the battery
at this time. Installing
the battery before the
controller is configured
can substantially
shorten battery life.
Install under power after
the controller
configuration is
complete.
(For more information,
refer to Battery
Installation/Replacement,
page 191.)
4
I/O will be installed later. See Page 66.