Multitron - Incubation Shaker
Operation
2. Place the tray on the door slide rails.
3. Push the tray between the guide rails over the front stop bar
up to the limit stop at the back of the incubation chamber. The
tray must audibly click into place behind the front stop bar.
4. Check whether the tray is placed properly behind the front
stop bar.
5. Equipment with 25 mm or 50 mm throw: Close the equip-
ment door.
When the door closes, the ejection levers lower and the tray is
lowered into the two cones. The tray is thus securely affixed to
the table.
6. Equipment with 3 mm throw: Ensure that the tray is cor-
rectly snapped into the two conical plugs on the table.
7. Equipment with 3 mm throw: Insert the knurled screw and
tighten it by hand. Tighten the knurled screw so that it cannot
come lose during operation.
8. Check whether the tray is securely affixed to the table.
ATTENTION
If the tray is not held in place securely on the table, the tray’s
movement may damage the interior of the equipment.
Do not start up the equipment unless the tray has been in-
serted correctly and affixed securely.
If you are using equipment with a 3 mm throw, make sure
the knurled screw is inserted and tightened correctly.