363-206-305 System Turnup:
NTP-010
Issue 3, June 2000 Page 5 of 8
DDM-2000 F
IBER
R
EACH
W
IDEBAND
S
HELF
DO ITEMS BELOW IN ORDER LISTED . . . . FOR DETAILS, GO TO
At the near end, remove the optical loop from the 27-Type OLIU
OC-1 line (1 or 2) (for example in Figure 1, OC-3 shelf MAIN 1,
OC-1 line 1) associated with the optical span being established.
At the other end of the optical span, remove the optical loop from
the associated 26-Type OLIU (for example, in Figure 1,
FiberReach MAIN-2 OLIU).
DLP-51410. Perform optical fiber connections and verification of the integrity of
the optical span being established.
11.
NOTE:
Shelves that are part of a subnetwork being partitioned into
multiple sreas require that the NSAP
AREA
field and level 2
IS-IS routing parameters of the ent-ulsdcc-l3 command
be set. See Section 11 “Commands and Reports” in
363-206-285,
DDM-2000 OC-3 Multiplexer, TARP Release
13 and Later, User/Service Manual - Volume I
and this
manual, for an explanation of the command parameters and
824-102-144,
Lucent Technologies 2000 Product Family,
Operations Interworking Guide for TARP Releases
, for an
explanation of the engineering rules for subnetworking
partitioning.
Use the ent-ulsdcc-l3 command to designate the NSAP
AREA
field and level 2 IS-IS routing, as required.
DLP-535
12.
NOTE:
The rtrv-pm-line command in the following procedure
displays performance monitoring data associated with the
OC-1 lines terminated on the system.
Perform end-to-end OC-1 line test.
13. Repeat this procedure for all OC-1 optical spans back to the host
OC-3 shelf.