363-206-305 System Turnup:
NTP-031
Issue 3, June 2000 Page 9 of 14
DDM-2000 F
IBER
R
EACH
W
IDEBAND
S
HELF
DO ITEMS BELOW IN ORDER LISTED . . . . FOR DETAILS, GO TO
18.
NOTE:
The rtrv-pm-line: command in the following procedure
displays performance monitoring data associated with the
OC-3 lines terminated on the system.
DLP-515Perform end-to-end OC-3 line test.
19. Repeat this procedure for all OC-3 optical spans being
established in the DDM-2000 OC-12/OC-3 network. Ensure that
the last optical span connected to the OC-12 host shelf is
connected to an OLIU in the opposite slot as the one in the first
OC-3 span (for example, slot 1 for the first span and slot 2(P) for
the second span).
20.
NOTE:
Establishing service requires that the proper slots in each
terminating node be properly equipped with the correct
circuit pack(s) for the type of service being established. It
also requires numerous cross connections in each of the
nodes representing the path of the required service.
Additionally, transmission tests should be performed to verify
the continuity and quality of the established circuit.
The FiberReach OC-3 linear extension is now ready for initial
service to be established.
Initial DS1 Service [System Turnup: NTP-004]
Initial T1 Service [System Turnup: NTP-013]
Initial HDSL Service [System Turnup: NTP-017]
Initial DS3 Service [System Turnup: NTP-025]
STS-3c Service [System Turnup: NTP-016]