363-206-305 Detailed Level Procedure:
DLP-517
Issue 3, June 2000 Page 3 of 4
DDM-2000 F
IBER
R
EACH
W
IDEBAND
S
HELF
12. Repeat this procedure fron Step 1 for any additional OC-3c circuits to be
tested.
13. STOP. YOU HAVE COMPLETED THIS PROCEDURE.
14. Has the 22D-U/22G-U/22G2-U/22G3-U/22G4-U OLIU circuit pack that failed
been replaced?
If YES, proceed to Step 17.
If NO, continue with Step 15.
15. Replace the 22D-U/22G-U/22G2-U/22G3-U/22G4-U OLIU circuit pack that
failed the test.
Reference: DLP-523
16. Repeat this procedure for the 22D-U/22G-U/22G2-U/22G3-U/22G4-U OLIU
circuit pack that failed.
17. Trouble may be in the LGX cross-connections or the shelf backlplane. If othe
alarms or trouble indications are present, refer to Trouble Clearing: IXL-001
to isolate the trouble. If no alarms or indications are present and a CIT is
available, usr the RETRIEVE commands (for example, rtrv-alm,
rtrv-hsty, etc.) to check for other trouble indications.
18. STOP. YOU HAVE COMPLETED THIS PROCEDURE.