363-206-305 Detailed Level Procedures:
Issue 3, June 2000 Page 1 of 2
DDM-2000 F
IBER
R
EACH
N
ARROWBAND
S
HELF
DLP-515
Perform Visual Inspection of the Secured Area
Telecommunications Applications Cabinet (STAC)
1. Verify that the STAC Cabinet is not damaged (see Figure 1).
2. If problems exist, contact responsible installation group.
3. Verify that there are no broken, bent, or misaligned contacts on the backplane
connectors.
4. If problems exist, contact responsible installation group.
5. Is one channel unit plug-in of any type available?
6. Check for a misaligned or bowed shelf by inserting a channel unit in the
leftmost and rightmost channel unit slots of top shelf. Remove the channel unit.
7. Check for a misaligned or bowed shelf by inserting a channel unit in the
leftmost and rightmost channel unit slots of bottom shelf.
8. Remove the channel unit.
9. STOP. YOU HAVE COMPLETED THIS PROCEDURE.
If YES, continue with Step 6.
If NO, proceed to Step 9.