8.02 Initial start-up
Before the initial start-up, clean the machine thoroughly and lubricate or fill the oil, see
chapter 12 Maintenance and Care!
Inspect the machine and in particular the electric lines and pneumatic connecting hoses
for possible damage.
Arrange for technical staff to check whether the machine may be operated at the existing
mains voltage and whether it is connected properly.
Do not operate the machine if there are any differences!
The machine must only be connected to a grounded socket!
Connect the machine to the compressed
air system and push the slide closure 1
upwards.
It must have a supply pressure of 6 bar.
Set this value if necessary, see chap-
ter 12.06 Monitoring / adjusting the air
pressure.
Fig. 8 - 07
1

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Pfaff 3519-5/01 and is the answer not in the manual?

Pfaff 3519-5/01 Specifications

General IconGeneral
BrandPfaff
Model3519-5/01
CategorySewing Machine
LanguageEnglish

Related product manuals