Operation
0140−1/A1
Winterthur Gas & Diesel Ltd.
1/ 1
Prepare the Cylinder Lubricating System
See 7218−1 Cylinder Lubrication Fig. 1).
1) Make sure that the engine is in the condition that follows:
D The engine control system (ECS) and remote control systems (RCS) are set
to on.
D The primary switches in the control box E44 (engine room) are set to on and
the ECS has selected cylinder lubrication.
2) Do the checks that follow:
a) Make sure that the ball valves are open.
b) Make sure that there is no air in the cylinder lubrication pumps (25_7230_C1_1
to 25_7230_C#_1).
c) Make sure that there is no air in the lubricating pipes to the lubricating quills.
You must only do the air removal procedure:
D Before the first commissioning
D After maintenance
D After a long shut-down period
D When there are operation problems (operation pressure, supply rate).
Prepare the Engine for Operation
2014