2-9. Allocation of Phases
The 6105A or 6100B is always L1 in a multiphase system. Auxiliary units are allocated
phase depending on which auxiliary control output they are connected to. The Auxiliary
unit connected to L2 Control Output becomes L2 etc. See the Users Manual for an
overview of instrument control and the user interface.
This section is a reference for the functions and locations of the 6100B front and rear
panel features, and provides brief descriptions of each feature for quick access.
Complete front-panel operating instructions and remote operating instructions for the
6100B are provided in the Users Manual.
Please read this information before operating the 6100B.
2-10. Connection and Power-Up Sequence
Power-Up
When working with poly-phase systems you should connect the control cables between
Auxiliary and Master units first. Then switch ON power to the Auxiliary units, then the
Master.
Power-Down
Turn off the Master unit first when powering down. Damage will not occur if the
sequence is not followed but error messages may show on the User Interface.