7 Initial Start-up
7.1 Ensuring safety
Follow the instructions below for safe commissioning of the machine.
Warning instructions are located before a potentially dangerous task.
Disregard of warning instructions can cause serious injuries!
Complying with safety warnings
Disregard of safety warnings can cause unforeseeable dangers!
Follow the instructions in chapter 3 “Safety and Responsibility”.
Commissioning work may only be carried out by authorized personnel!
Make sure that no one is working on the machine.
Ensure that all service doors and panels are locked.
Further information Details of authorized personnel are found in chapter 3.4.2.
Details of dangers and their avoidance are found in chapter 3.5.
7.2 Before initial start-up (or recommissioning)
Incorrect or improper commissioning can cause injury to persons and damage to the machine.
7.2.1 Instructions to be observed before commissioning or recommissioning
The initial start-up of every machine takes place at the factory. Every machine is also given a
trial run and passes a careful check.
Commissioning may only be carried out by authorized installation and service personnel who
have been trained on this machine.
Remove all packing materials on and in the machine.
Observe the machine during the first few hours of operation to ensure that it is operating cor‐
rectly.