363-206-305 System Turnup:
NTP-009
Issue 3, June 2000 Page 5 of 14
DDM-2000 F
IBER
R
EACH
W
IDEBAND
S
HELF
DO ITEMS BELOW IN ORDER LISTED . . . . FOR DETAILS, GO TO
At the near end OC-3/OC-12 host node, remove the optical loop
from the 27-Type OLIU OC-1 line (1 or 2(P)) being used for the
OC-1 ring configuration (for example, in Figures 7 and 8, OC-3
shelf Node 5, slot FUNCTION UNITS A 1, OC-1 line 1). At the
other end of the optical span being established, remove the
optical loop from the associated 26-Type OLIU (for example, in
Figures 7 and 8, FiberReach MAIN-1 OLIU).
9.
NOTE:
The section data communication channel (DCC), used for
far-end communications, must be enabled at each network
element (shelf) optical interface being tested in order for the
end-to-end line tests to work. Default condition for the DCC
channel is "enabled.” If it has been disabled, use the
set-fecom command at each shelf to enable far-end
communications.
At each shelf, use the set-fecom:
address
:com=enabled
command to ensure far-end communications (fecom) is enabled.
DLP-51410. Perform optical fiber connections and verification of the integrity of
the optical span being established.
11.
NOTE:
Shelves that are part of a subnetwork being partitioned into
multiple sreas require that the NSAP
AREA
field and level 2
IS-IS routing parameters of the ent-ulsdcc-l3 command
be set. See Section 11 “Commands and Reports” in
363-206-285,
DDM-2000 OC-3 Multiplexer, TARP Release
13 and Later, User/Service Manual - Volume I
and this
manual, for an explanation of the command parameters and
824-102-144,
Lucent Technologies 2000 Product Family,
Operations Interworking Guide for TARP Releases
, for an
explanation of the engineering rules for subnetworking
partitioning.
Use the ent-ulsdcc-l3 command to designate the NSAP
AREA
field and level 2 IS-IS routing, as required.