363-206-305 Circuit Order:
NTP-033
Issue 3, June 2000 Page 11 of 12
DDM-2000 F
IBER
R
EACH
W
IDEBAND
S
HELF
DO ITEMS BELOW IN ORDER LISTED . . . . FOR DETAILS, GO TO
46.
NOTE:
A CP removed alarm will occur when the MAIN-1 OLIU is
removed from the starting Node.
At the starting Node (Node 1), remove optical fibers and lift the
faceplate latch of MAIN-1 OLIU, then remove MAIN-1 OLIU.
47.
NOTE:
When the 29-Type OLIU is installed, an
unexpected CP type status, OLIU CP failed, and
OLIU connector failed alarm will occur. The
inc. OC12 LOS alarm should clear at both ends of the
span. The inc. VT and STS AIS alarms clear
downstream.
Install a 29-Type OLIU into MAIN-1 OLIU slot and reconnect
optical fibers.
48. At the starting Node 1, connect the OC-12 faceplate connector
between MAIN-1 and MAIN-2 29-Type OLIUs.
49. Momentarily depress the UPD button on the SYSCTL or execute
the update (upd) command at the starting Node.
50. If an OC-12 shelf is to be added to this new ring configuration,
Use the procedures of NTP-021 in 363-206-295,
DDM-2000
OC-12 Multiplexer, TARP Release 7, User/Service Manual
(TOP)—Volume II
or
NTP-026 in 363-206-285,
DDM-2000 OC-3
Multiplexer, TARP Release 13 and Later, User/Service Manual
(TOP)—Volume II
.