DLP-529
: Detailed Level Procedure 363-206-305
Page 2 of 6 Issue 3, June 2000
DDM-2000 F
IBER
R
EACH
W
IDEBAND
S
HELF
5.
NOTE:
Under normal conditions, when the first battery is connected, the
following occurs: (a) test set
TIME
display indicates
00 MIN: 00 SEC
; (b)
status display indicates which test set
BATT
plug that battery is
connected to, status of the battery (
GOOD
or
REPLACE
), and the
READY
indicator lights; (c) test set fan operates.
At test set connector head, connect battery lead to
BATT 1, 2, 3
, or
4
plug
being tested.
6.
!
WARNING:
Damage will occur if test set is operated without fan operating.
Does test set fan operate?
If
YES
, proceed to
Step 15.
If
NO
, continue with
Step 7.
7. Connect battery lead to remaining
BATT
plugs, one at a time, and note if fan
operates.
8. Did test set fan operate for any
BATT
plug connection?
If
YES
, proceed to
Step 11.
If
NO
, continue with
Step 9.
9.
NOTE:
The test set is intended to test fully charged batteries. Before new
batteries or replacement batteries are tested, a minimum of two days
must have passed between the time the batteries were put on high rate
charge and this test is made.
Disconnect lead. Using a different battery pack, connect battery lead to any
BATT
plug.
10. Does test set fan operate?
If
YES
, proceed to
Step 15.
If
NO
, proceed to
Step 35.