8 - 1
Mounting and commissioning the machine
8 Mounting and commissioning the machine
After unpacking the machine, check it for any transport damage. In case of damage, inform
the shipping company and the responsible PFAFF dealer.
The machine must only be mounted and commissioned by qualified personnel!
All relevant safety regulations are to be observed!
8.01 Mounting
At the machine’s location, there must be a stable and horizontal surface as well as suitable
electricity and compressed air supplies (see chapter 3 Specifications).
● Lift the machine with a forklift from the shipping pallet.
For machines without vertical adjustment:
● Align the machine horizontally just above the floor and move the four legs accordingly
before setting the machine down on the ground.
For machines with vertical adjustment:
● Set down the machine on the ground and align it by turning the four spindles.
The vertical adjustment is available as an optional feature.
Fig. 8-01 shows a machine with vertical adjustment.
Fig. 8 - 01