8 - 3
Mounting and commissioning the machine
8.04 Commissioning
Clean the whole machine thoroughly and check the electrical leads and pneumatic
connecting tubes for any damage.
Make sure that the mains voltage corresponds to the connection voltage of the machine
(see chapter 3 Specifications). If the mains voltage and the connection voltage differ,
the machine must not be operated under any circumstances.
Have specialists connect the machine to the mains.
Oil the machine and/or fill with oil (see
chapter 12 Care and maintenance).
Connect machine to the compressed air system. The manometer on the air filter/
lubricator unit must display a pressure of 6 bar. If necessary, set to the correct value
(see chapter 12.05 Checking / regulating air compression).
Fig. 8 - 04
1

Table of Contents