Operation instructions
SIPOS SEVEN: PROFITRON, HiMod
Page 34 Y070.302/EN
7 Commissioning
7.1 Basic information
7
Commissioning
7 Commissioning
7�1 General information
■
Before performing any work on the installed and electrically connected actuator, check with the
plant personnel in charge that commissioning may not cause any fault of the plant or hazards to
persons.
■
If a cut-off mode or torque setting is selected that is not appropriate for the valve, the valve may
be damaged!
■
If LOCAL control is changed to REMOTE control, the actuator is operated if an operation com-
mand by the automation system (DCS) is present!
■
There are hazardous voltage levels within the actuator.
It is recommended that the services and support of the responsible SIPOS Aktorik service centers
are utilized for all planning, installation, commissioning and service tasks.
Ensure prerequisites for commissioning
Check and ensure the following points after assembly or during revision and inspection:
■
The actuator is correctly assembled.
■
Allxingscrewsandconnectingelementsarermlytightened.
■
The grounding and equipotential bonding has been correctly implemented.
■
The electrical connections have been correctly implemented.
■
All protection against accidental contact has been implemented for moving or live parts.
■
Neither the actuator nor the valve is damaged.
■
Thepermittedtemperaturerangefortheactuatorismaintainedandheatdissipationfromthenal
control element is also taken into account.
Furtherchecksarealsonecessaryinaccordancewiththeplant-specicconditions.
Prior to commissioning
■
Set language if the texts in the display are not shown in the desired language, refer to chapter
„5.2 Language selection“ on page 29.
■
Enable access rights for at least user level 3‚ Supervisor‘, refer to chapter „6 User management“
on page 31.