12.4 Maintenance schedule – overview
Carry out maintenance work when the first interval is reached.
The times, continuous services or maintenance intervals specified in
any third party documentation shall have priority.
Before commissioning
Specialist
workshop
Check and service the
hydraulic hose lines.
The inspection has to be recorded by the
owner/operator.
Section 12.5.3
Checking the oil level in the Vario gearbox Section 12.4.1
Checking the inflation pressure of the running
gear tyres
Section 12.4.4
Check the tyre inflation pressure on the support
wheels
Section 12.4.5
Check the tyre inflation pressure on the press
rollers
Section 12.4.6
After the first
10 operating hours
Specialist
workshop
Checking the tightening torques of wheel nuts Section 12.5.1
Specialist
workshop
Check and service the
hydraulic hose lines.
The inspection has to be recorded by the
owner/operator.
Section 12.5.3
After the first
20 operating hours
Specialist
workshop
Check all screw connections for a secure fit. Section 12.6
10 operating hours
after a wheel change
Specialist
workshop
Checking the tightening torques of wheel nuts Section 12.5.1

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Amazone Condor 12001-C and is the answer not in the manual?

Amazone Condor 12001-C Specifications

General IconGeneral
BrandAmazone
ModelCondor 12001-C
CategoryFarm Equipment
LanguageEnglish

Related product manuals