4. Loosen the tension belt
from the top link
and lower link
and remove it.
CMS-I-00005312
5. When the hydraulic coulter pressure system is
closed again,
connect the hydraulic plugs
on both
implement sections to a vent hose.
6. To set the coulter pressure to zero,
refer to the ISOBUS operating manual "Adjusting
the coulter pressure".
7. Switch on the fan at 2000 rpm.
NOTE
Ensure that the oil supply in the hydraulic unit is
sufficient.
8. To vent the coulter pressure system on both
sides,
move the seeding units on both implement
sections up and down consecutively with a crane.
CMS-I-00004129
6.4.23.4.4 Establishing the air and fertiliser supply on the rear hopper with central drive
1. Open the sliding shutter
on the fertiliser
metering unit.
CMS-I-00003915
CMS-T-00005487-B.1
6 | Preparing the machine
Preparing the implement for operation
MG6660-EN-II | D.1 | 27.09.2021