See Management module on page 4-61 section.
7. Remove all cables for the failed management module.
8. Release the blue lock tab and pull the lever, as shown below.
9. Holding the management module, carefully slide out the management
module from the chassis and place it on an anti-static mat.
Figure 5-130 Removing a management module
Installing a management module
1. Put on an anti-static wrist strap.
2. Reverse the removal procedure to install the management module.
3. Verify that the Power LED and MSR LED are blinking in green after Power
LED blinked in green.
4. Connect the LAN cable to the master management module and start the
Web console.
5. Synchronize the internal LAN between the primary management module
and the target one.
Select Resources tab on the web console and select Modules > All
Modules > Management Modules.
6. Click Action and select Sync Internal LAN.
7. The confirmation dialog box appears. Click OK. Synchronizing internal
address will start.
Replacing parts
5-101
Hitachi Compute Blade 500 Series System Service Manual