Mounting and installation of the compact control panels
5
223 |
Building Technologies
5.33 Batteries
Guidelines
WARNING
Switching batteries in parallel
Risk of explosion and fire
● Never connect batteries in parallel!
If you need more power, you must use batteries with a higher capacity.
● The batteries must meet the predefined specifications. You will find further
information in document 008843.
● Batteries must be installed so that they cannot leak. The openings for cables in
the back box must not be broken out (EN 60950-1).
● If two housings are installed and attached one under another, the batteries
must be installed in the bottom housing.
Mounting steps
NOTICE
Potential damage to hardware
● The supplied jumper wire must not be connected until the time of
commissioning.
● Note the polarity of the supply: Red cable = positive pole; blue cable =
1. Place the batteries on base of the rear panel.
2. Connect the unconnected cable ends of the secondary cabling of the power
supply to the poles of the batteries:
3. Red cable on positive pole of the left battery
4. Blue cable on negative pole of the right battery
a The station is then ready for commissioning. You will find information about