Mounting and installation FC2080
6
262 | 354
6 Mounting and installation FC2080
6.1 Mounting procedure
The following mounting processes are described in the following chapters:
● Assembling the housing (19", pedestal cabinet) FH2080-AA
● Installing the carrier components
● Installing all other components
Prerequisites
● All parts have been checked to make sure they are complete and intact.
● Mains connection is current-free
Mounting procedure
The installation procedure described below is an overview and is largely an
optimized procedure but does not have to be adhered to exactly.
WARNING
Mortal danger due to electric shock
● Before working on the station check that the mains supply cable is
disconnected from the power supply.
● Check to make sure that the mains is secured against inadvertently being
switched on.
● Always connect the grounding (PE) to the mains supply cable first.
● The components must be installed by a qualified electrician or a trained
NOTICE
● Perform all mechanical work before installing the components.
● Insert possible plug-in cards only after installing all the card cages.
Do not connect up the batteries after installation but wait until commissioning.
1. Position the base such that the cable can be routed from the right-hand side of
the housing interior.
2. Fit the base securely to the substructure with 4 screws and dowels.
3. Remove the cover plates at the bottom of the cabinet to gain easy access to
the mounting points.
4. Place the cabinet on the base and connect it with 4 screws.
5. If the planned installations impair the accessibility of the grounding bar, move it.
It must be possible to install the cable insulation and strain relief.
6. After inserting the cable, seal the base by screwing down the plates again to
ensure EMC protection.