2-3
Installation Verification Operator Manual 920011-649
� Measure building hot water supply temperature downstream of
Dual Pre-Filter and Pressure Regulator Assembly (required
accessory). Temperature must be within range specified on
equipment drawing (920-011-656).
NOTE: Temperature range specified on equipment drawing gives
optimal cycle time. But an alarm occurs if temperatures are above
49°C (120°F).
• If water temperature is below minimum temperature:
Install a 38-57
L (10-15 gal) fast-recovery hot water heater.
Supply hot water heater with hot water. Set water heater to
60-70°C (140-160°F). Run water heater output into an anti-
scald mixing valve.
NOTE: Water heater and mixing valve must be installed
upstream of Dual Pre-Filter and Pressure Regulator
Assembly.
• If water temperature is over maximum temperature:
Install a temperature control valve, such as STERIS part
number A1002, upstream of Dual Pre-Filter and Pressure
Regulator Assembly (required accessory).
� Connect drain line to building waste line as specified on
equipment drawing.
� Electrical supply for processor is as specified on equipment
drawing.
� Air supply for processor is as specified on equipment drawing.
� Floor underneath processor has a nonslip and noncombustible
surface or is covered with a metal sheet extending to the outer
edges of the processor.
� Order a supply of Reliance dry chemistry containers, STERIS
chemical indicators for the Reliance EPS, CIP 200
®
Acid-Based
Process and Research Cleaner and Klenzyme
®
Enzymatic
Presoak and Cleaner from STERIS. Refer to SECTION 8,
RECOMMENDED SPARE PARTS AND CONSUMABLE PRODUCTS, or
contact STERIS for ordering information.
IMPORTANT: After a few weeks of operation, inspect processor
for leaks. Retighten all clamps and connections.
WAR
NING – POSSIBLE FIRE
HAZARD: When processor is
installed on a combustible
floor, floor must be covered
with a metal sheet extending
to outer edges of processor.