G10 Hardware Maintenance Guide 7.13.2 142
5
Maintenance Guidelines
Rev. 002-140228
Note that some new AC power units do not have an on/off switch.
Figure 5.55 - DC Power Switch on Disk Array
5. Reconnect the cables.
6. Power on the probe. See the probe start up procedure for details on powering
u
p th
e probe.
7. Check that the FRU OK LED (back) is green, indicating that the controller has
completed initializ
ing, is
online, and is operating normally.
8. See the Iris
Inst
allation and Upgrade Guide to configure the G10 Probe and
complete the disk array replacement. Contact Tektronix Communications
Customer Support for assistance.
Tektronix Communications | For Licensed Users | Unauthorized Duplication and Distribution Prohibited

Table of Contents

Other manuals for Tektronix GeoProbe G10

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Tektronix GeoProbe G10 and is the answer not in the manual?

Tektronix GeoProbe G10 Specifications

General IconGeneral
BrandTektronix
ModelGeoProbe G10
CategoryAccessories
LanguageEnglish