Figure 62 On-process ramp PDT menu conguraon items
Onprocess ramp is enabled by seng a ramp delay me greater than zero. This me is
the me delay between the pump speed increases. The ramp step size determines the
size of each step. The pump speed will not exceed the maximum allowed pump speed.
9.9 How to set up the DP clean
The DP clean set sequence can be used to clean the dry pump of systems that are ed
with the high ow purge and solvent ush kit.
Before using DP clean, ensure that the high ow purge and solvent ush kit is set up as
described in High ow purge and solvent ush set up on page 51. Also, refer to Dry pump
clean on page 63.
The DP clean process is run while the dry pump is in Green mode/standby mode. By
default, the DP Clean runs for 20 minutes with the dry pump running at 80 Hz with no
inlet purge.
The following ow chart shows the funconal behaviour of dry pump clean:
Page 141
M58800880_H - Pump display terminal

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Edwards GXS Series and is the answer not in the manual?

Edwards GXS Series Specifications

General IconGeneral
BrandEdwards
ModelGXS Series
CategoryWater Pump
LanguageEnglish

Related product manuals