Versiv Series Cabling Certification Product Family
Technical Reference Handbook
544
To Change the Tests in a Project
When you use a project, you usually do only the tests that the
project specifies. You select these tests from the list on the
CHANGE TEST screen in the project.
If necessary, you can add a test to the project or change the
settings for a test in the project.
To select a different test in the project
1 On the home screen, tap the test setup panel.
2 On the CHANGE TEST screen tap the test you want to do. See
Figure 201 on page 533.
3 Tap USE SELECTED.
To add a test to a project
1 On the home screen, tap the test setup panel or the PROJECT
panel.
2 Tap NEW TEST.
3 On the TEST TYPE screen, tap a test.
4 On the TEST SETUP screen, change the test settings as
necessary, then tap SAVE.
To include a fiber test in the % Tested value
If you add an OptiFiber Pro OTDR, CertiFiber Pro loss length,
FiberInspector, or FaultMap test to a project, but do not select the
test on the CABLE ID SETUP, EDIT CABLE IDs, or IMPORTED IDs
screen, the results you save for the test do not affect the %
Tested value.To include a test in the % Tested value
1 On the home screen, tap the PROJECT panel, then on the
PROJECT screen, tap a fiber ID set that has a First and Last ID.