7.2 Installing memory modules
I If liquid cooling is installed, first prepare the memory modules as
described in section "Cooling pads on the memory modules" on
page 199.
7.2.1 Preliminary steps
Perform the following procedures:
Ê "Disabling SVOM boot watchdog functionality" on page 54
Ê Locate the desired server node.
Ê "Shutting down the server node" on page 39
Ê If applicable, remove all external cables from the server node.
Ê "Removing the server node from the server enclosure" on page 40
Ê Disconnect the SATA cable(s) from the connectors on the system board
described in section "Cabling for HDD 2.5"" on page 208, and take it out of
the chassis.
Ê "Removing the memory slot air ducts" on page 48
Ê Identify the correct memory slot according to the mounting order described
in section "Memory sequence" on page 118.
Upgrade and Repair Unit
(URU)
Hardware: 5 minutes
Tools: tool-less