Power On the Server (Oracle ILOM)
192 SPARC T5-8 Server Service Manual • November 2015
4.
Start the system.
See “Power On the Server (Oracle ILOM)” on page 192.
Related Information
■
“Power On the Server (Oracle ILOM)” on page 192
■
“Power On the Server (Power Button)” on page 193
Power On the Server (Oracle ILOM)
The start up process depends on the last power state of the server and on Oracle ILOM policy
settings. You must check to see if the system is running before you issue the start /SYS
command.
1.
Log in to Oracle ILOM.
See “Log In to Oracle ILOM (Service)” on page 28.
2.
Determine if the system has been started.
-> show /System power_state
■
If the system is running, go to the verification task for the component that you replaced.
■
If the system is not running, go to Step 3.
3.
Start the system.
-> start /System
4.
Determine your next step.
■
If you are servicing a component, return to the procedure for that component.
■
If you are upgrading the server, return to “Server Upgrade Process” on page 59.
Related Information
■
“Verify the Battery” on page 126
■
“Verify the DIMM” on page 80
■
“Verify the Processor Module” on page 70
■
“Verify the Rear I/O Module” on page 178
■
“Verify the Service Processor Card” on page 114
■
“Verify the System Configuration PROM” on page 120
■
“Server Upgrade Process” on page 59