Verify the Rear Chassis Subassembly
188 SPARC T5-8 Server Service Manual • November 2015
Components Links
Power supplies “Install a Power Supply” on page 137
Main module “Install the Main Module” on page 95
Processor modules (bottom to top) “Install a Processor Module or Processor Filler
Module” on page 67
Cables According to their lables
8.
Power on the server.
See “Returning the Server to Operation”.
9.
Verify the installation.
See “Verify the Rear Chassis Subassembly” on page 188.
Related Information
■
“Remove the Rear Chassis Subassembly” on page 182
■
“Verify the Rear Chassis Subassembly” on page 188
Verify the Rear Chassis Subassembly
1.
Ensure that you have completed the following:
■
Applied power to the server.
See “Connect the Power Cords” on page 191.
■
Started the system.
See “Power On the Server (Oracle ILOM)” on page 192.
2.
Log in to Oracle ILOM.
See “Log In to Oracle ILOM (Service)” on page 28.
3.
Start the faultmgmt shell.
-> start SP/faultmgmt/shell
Are you sure you want to start the faultmgmt shell (y/n)? y
faultmgmtsp>
4.
Use the fmadm faulty command to determine if the server is operating normally.
■
If a fault was detected, see “Diagnostics Process” on page 25.
■
If no fault was detected, the rear chassis subassembly was installed successfully.