3) Leveling instrument roughly by circular level
(Same as The section above that discusses centering and leveling with plumb
bob)
4) Leveling instrument accurately by tubular level
(Same as The section above that discusses centering and leveling with plumb
bob)
5) Centering and leveling accurately
Loosen center connection screw slightly and move instrument
horizontally(Don’t rotate instrument) through observation to optical plummet,
making the instrument aim at station accurately. Tighten the center connection
screw and leveling instrument accurately again.
This operation should be repeated till the plumb aims at station accurately.
☆Fully charge the battery before measurement.
☆Cut off the power before removing the battery.
▶Step mounting the battery
1. Insert the battery to the instrument.
2. Press the top of the battery until you hear a click sound.
1. Press the button downward.
2. Remove the battery by pulling it toward you.
●Battery information
——Power is adequate, operating available.
——The battery can be used for 4 hours when this symbol first appears. If you
cannot master the consumed time, you should prepare a spare battery or charge
the battery before using.
— —
End of the operation as soon as possible and replace the battery and
charge if running out of power.
— — It takes several minutes for the instrument to shut down when this
symbol first appears. The battery has few power now and should be replaced an
recharged.
Notice:
1
The operating time of battery depends on environmental conditions such as
ambient temperature, time and times of charging and so on the battery is
suggested to be prepared or charged ahead before operation to keep it safety.
2
The battery symbol only indicates power capability undercurrent measurement
mode. The remained capacity of the battery shown under current mode does not