APS-Series 120 Operating Instructions v320 EN
4.9.2 MV Skid not monitored by the APS
NOTICE
Failure during grid connections due to missing cable bridge and
resistor!
If the APS used without a MV skid or monitored external, the customer
must connect delivered cable bridge and a resistor.
• The cable bridge and resistor located in Section +C3 for
1-2 APUs or Section +C6 for 3-4 APUs.
• Use only the delivered cable bridge and resistor.
Procedure:
1. Connect the delivered cable bride and resistor to provided terminals
(Figure 101).
Figure 101: Connection of MV skid interfaces when not monitored by the APS
MV switchgear simulation ON
Resistor simulation PT100