Original Operating Instructions
APS Series Outdoor Hybrid Inverter
Installation
APS-Series 120 Operating Instructions v320 EN
Page 91 of 213
4.5 MV Skid (Accessory)
4.5.1 Mounting MV Skid
Required material (part of accessory MV skid):
8 x M12 hexagon nuts
8 x M12x45 mm hexagon screws
16 x washers
2 x connection plates
Procedure:
1. Position the MV skid so that the APS carrier and MV skid carrier can be
connected (Figure 76).
2. Join support together with connecting plates and fixing means.
3. Tighten the hexagon nuts with a torque of 75 Nm.
Figure 76: Attaching the MV skid to APS
Pos.
Description
1
APS
2
MV skid
3
Connecting plate
4
MV switchgear
5
MV transformer