Original Operating Instructions
APS Series – Outdoor Hybrid Inverter
Commissioning
APS-Series 120 Operating Instructions v320 EN
5.1 Preparing Commissioning
Requirements:
• Conditions for operation must be fulfilled (Section 12.2).
• An initial setup via the user interface is necessary before commissioning.
Figure 103: Routing temperature sensor
Figure 104: Position temperature sensor
Figure 105: Current transformers on inductor
connections (Sections +C3, +C6)
Figure 106: Distance between current transformer
cable and inductor
Inductor (APU 1) with 3 current transformers
Inductor (APU 2) with 3 current transformers
Inductor (APU 3) with 3 current transformers
Inductor (APU 4) with 3 current transformers