NOTICE
Damage to the product due to improper foundation!
An improper foundation can have influence on stability and IP tightness
of the product.
• The product must be placed on concrete foundation.
• The APS carrier must be placed on a one-piece foundation
(Figure 35).
• The foundation support points of the APS carrier must be within
the height tolerance of ± 1 millimetre.
• The foundation must be made of homogeneous construction.
• The whole foundation must be levelled earlier.
• Before placing the product please check concrete foundation for
any exhibit visible distortion, like bulges, cracks or non-
homogeneity in own structure. All such defects must be
eliminated.
• The foundation must be made and have final acceptances in
accordance with the applicable building regulations.
• After placing the product, it is necessary to manually and visually
check the correctness of the fixing of the main points.
• Perform all activities described in Section Obligatory Activities
after Transport.
NOTICE
Damage to the product due to overheating!
Insufficient cooling air can lead to damage or overheating of the
product.
• Ensure that sufficient cooling air at the installation site.
Requirements for the installation site:
• Ensure that there is sufficient room for installation, mounting, operation and
repair (Figure 52).
• Around the APS and MV skid ensure that there is a service area with a depth of
two meters. This must be at the height of the cabinet.
• Ensure that the minimum required distances for escape routes must be followed
according to applicable local regulations and standards.
• The product must be properly positioned on the foundation.
• Required environmental conditions must be fulfilled at all times (see below).