Chapter 13 Motherboard Unit Replacement 13-11
13.1.8 Securing the Server
1. Install the CPU modules and filler panels.
See Section 12.1.3, “Installing the CPU Module” on page 12-6.
2. Install all memory boards.
See Section 11.1.3, “Installing the Memory Board” on page 11-6.
3. Install the top cover.
This step includes sliding the server in to the equipment rack and restoring the
antitilt features to their original position. See Section 5.2.2, “Replacing the Top
Cover” on page 5-8.
4. Power on the server.
This step includes reconnecting power cables, verifying the state of the LEDs, and
turning the keyswitch to the Locked position. See Section 4.4.2, “Powering the
Server On Using Software” on page 4-13.
Note – If the Oracle Solaris automatic booting is set, use the sendbreak -d
domain_id command after the display console banner is displayed but before the
system starts booting the operating system to get the ok prompt.
5. Confirm the hardware.
This step includes running programs to be certain all components are mounted
again and then booting the operating system.
Refer to Section 4.3.2, “Verifying Hardware Operation” on page 4-9 for more
information.