Chapter 2 Installation Preparations
Introduction
This chapter introduces the preparations before installing the device, including the engineer
requirements installation site environment requirements, cabinet and rack requirements, and
unpacking. This chapter includes the following sections:
l Installation site environment requirements
l Cabinet requirements
l Rack requirements
l Verifying the parts received
l Unpacking
Installation Site Environment Requirements
The SG-6000X-Series device is designed for indoor use and the indoor environment should be a
trusted location only available to the trusted employees . To ensure the normal operation and to
prolong the service lifetime, the installation site must meet the requirements below.
Temperature/Humidity Requirements
The ambient temperature and relative humidity in the installation site should be maintained at
acceptable levels. The requirements are shown as below:
Item Requirements
Ambient Tem-
perature
When the device is working, the requirement is
between 0ā and 40ā;
When the device is being stored, the requirement is
between -20ā and 70ā.