3. Unpacking, Installation and Wiring
3-6
3.3. Wiring
3.3.1. Connection of Cable Set
Caution : Do not cut the Motor cable to change the length shorter or longer or do
not hook it up to other cable. You need to separately purchase the cable
with specified length.
The standard cable length is available in 1, 2, 3, 4, 5, 6, 8, 10, 15, 20 and
30 meters.
Caution : Do not place the power lines (AC main power and Motor cable) and the
signal lines in close proximity. Do not tie wrap them and not to put in the
same duct or conduit.
Caution : When considerable vibrations are applied to the cable, fix the cable near
the connector so that no stress is applied to the connector part.
Fig 3-6: Connection of cable set
To CN3
To CN4
To ground terminal