6 Move the prism according to
the direction of the arrow to
make the value of △ equal
0m.
Arrows Meaning:
↓ : Move the prism close to the
station.
↑: Move the prism far away the
station.
In the process of staking out, if
using the Repeat Measurement
or Tracking Measurement, the
calculation of the differences
between measured point and
stakeout point can be displayed
in real time and convenient.
○
7 It means the current prism
position is effective stakeout
point while both the△Hz and △
are 0.
△ Display as dig or fill data.
↓ : The value expresses the
depth of needed to dig.
↑ : The value expresses the
height of needed to fill.