Commissioning
5.2 Preparing for commissioning
Converter with the CU240B-2 and CU240E-2 Control Units
128 Operating Instructions, 01/2016, FW V4.7 SP6, A5E34259001B AC
5.2
Preparing for commissioning
5.2.1
Collecting motor data
Before starting commissioning, you must know the following data:
Which motor is connected to the inverter?
Note down the Article No. of the motor and the motor’s nameplate data.
If available, note down the motor code on the motor’s nameplate.
In which region of the world is the motor to be used?
- Europe IEC: 50 Hz [kW]
- North America NEMA: 60 Hz [hp] or 60 Hz [kW]
How is the motor connected?
Pay attention to the connection of the motor (star connection [Y] or delta connection [Δ]).
Note the appropriate motor data for connecting.