Commissioning
5.3 Quick commissioning using the BOP-2 operator panel
Converter with the CU240B-2 and CU240E-2 Control Units
Operating Instructions, 01/2016, FW V4.7 SP6, A5E34259001B AC
133
Starting quick commissioning
Carrying out quick commissioning
Preconditions
The power supply is switched on.
The operator panel displays setpoints and actual values.
Proceed as follows to carry out quick commissioning:
Press one of the arrow keys u
ntil the BOP-2 displays the "SETUP" menu.
In the "SETUP" menu, press the OK key to start quick commissioning.
If you wish to restore all of the parameters to the factory setting before
the quick commissioning:
Switchover the display using an arrow key: nO → YES
When selecting an application class, the inverter assigns the motor
control with the appropriate default settings:
Standard Drive Control (Page 135)
Dynamic Drive Control (Page 138)
If you select this setting or if no application class is
listed:
Expert (Page 141)