Advanced commissioning
6.7 Application-specific functions
Converter with the CU240B-2 and CU240E-2 Control Units
280 Operating Instructions, 01/2016, FW V4.7 SP6, A5E34259001B AC
Switching units with STARTER
Precondition
The inverter must be in the offline mode in order to change over the units.
STARTER shows whether you change settings online in the inverter or change offline in the
PC (
/ ).
You switch over the mode using the adjacent buttons
in the menu ba
r.
To change over the units with STARTER, proceed as follows:
1. Select the configuration
2. Go to the "Units" tab in the configuration screen form to change over the units
3. Changing over the system of units
4. Select process variables of the technology controller
5. Adapting to the line supply
The inverter signals that offline,
other units and pr
ocess variables
are set than in the inverter itself.
Accept these settings in the inver
t-