Commissioning
5.3 Quick commissioning using the BOP-2 operator panel
Converter with the CU240B-2 and CU240E-2 Control Units
146 Operating Instructions, 01/2016, FW V4.7 SP6, A5E34259001B AC
Procedure when using the BOP-2 operator panel
To start the motor data identification, proceed as follows:
1.
Press the HAND/AUTO key.
⇒ The BOP
-2 displays the symbol for manual operation.
2.
Switch on the motor.
3.
During motor data identification, "MOT
-ID" flashes on the BOP-2.
4.
If the inverter again outputs alarm A07991, then it waits for a new ON co
m-
mand to start the rotating measurement.
If the inverter does not output alarm A07991, proceed to step 7.
5.
Switch on the motor to start the rotating measurement.
6.
During motor data identification, "MOT
-ID" flashes on the BOP-2.
The motor data identification can take up to 2 minutes depending on the rated
motor power.
7.
Depending on the setting, after motor dat
a identification has been completed,
the inverter switches off the motor
- or it accelerates it to the currently set
setpoint.
If required, switch off the motor.
8.
Switch the inverter control from HAND to AUTO.
You have completed the motor data identification.