OSx Station Control 2-15SIMATIC PCS 7 OSx 4.1.2 Operator
When Role_Change to Primary Executes This command is only
executed when the following conditions are true.
• The selected OSx station is not in the process of resynchronizing.
• The selected OSx station is not out o f sync.
• The selected OSx station is a supervisory station.
Or,
• The selected OSx station is not in the process of resynchronizing.
• The selected OSx station is not out o f sync.
• The selected OSx station is an operator station, but there are no active,
non-resynchronizing supervisory stations that are in sync to choose.
Or,
• The selected OSx station is not in the process of resynchronizing.
• The selected OSx station is not in sync, but there are no active,
non-resynchronizing supervisory stations that are in sync to choose.
• The selected OSx station is either a supervisory or an operator station.
And,
• No other OSx station in the system is synchronizing to the primary.
• All BCL/RDT programs have g one idle during the role-change waiting
period.
• All reports have finished executing during the role-change waiting
period.
When Role_Change to Backup Executes This command is only
executed when the following conditions are true.
• No OSx station in the system is synchronizing to the primary.
• The selected OSx station is not out o f sync.
• The selected OSx station is a supervisory station.
• The local OSx station has an active primary in its database.