Commissioning Manual
6FC5397-4EP10-0BA8, 07/2018
205
You can check the commissioning status via the status symbols from the main screens of the commissioning wizards.
Completed task
Current task
Partially completed task group
Uncompleted task
The diagram below shows the general commissioning procedure for the NC.
Commissioning the prototype machine
Note
The control system constantly creates restoring points during operation. In case of data los
s due to power failure or other
problems, the control system automatically restores the last autosaved system data upon startup with an alarm appearing on
the screen.
Note
Before starting the machine commissioning with the commissioning wizard, make sur
e MD20050, MD20070, and MD35000