July 29, 2013, 715003794 Rev. B 83
3 Prepare the e2695 Separations
Module for Operation
Power-on the separations module
Power-on the separations module by moving the power switch (located at the
top of the left-hand side panel) to I. The start-up diagnostic tests begins.
Startup diagnostic tests
On startup, the separations module performs the following functions and
tests:
•CPU board
Memory (RAM and ROM)
•Keypad
•Display
External communication
Digital signal processor (DSP)
Contents:
Topic Page
Power-on the separations module ................................................... 83
Operating overview.......................................................................... 84
Configure the separations module .................................................. 91
Prepare the solvent management system....................................... 103
Prepare the sample management system for operation ................ 107
Procedures for preparing the separations module for operation... 112
Power-off the separations module................................................... 114