Z100-TYPE HARDWARE
12.
13.
14.
Drill the pilot holes for the upper- and lower-slotted openings on the right side of
new support and start the screws.
Repeat steps 9, 10, 11, and 12 until all connector modules (20 maximum) and the
Z9A support (see Note) are installed.
Note: The Z9A support provides a patch cord channel for the last connector
module installed.
If you are installing a multi-section cross-connect field, locate the position of the
first connector module on the floor plans and repeat the procedure from step 2 for
each section.
NOTES:
1.
EACH CONNECTOR MODULE AND THE Z9A
SUPPORT IS 5 INCHES (12.7 CM) WIDE.
2.
THIS DISTANCE IS FROM THE FLOOR TO
THE BOTTOM OF THE Z9A SUPPORT
Figure 2-26. Cross-Connect Field and Cable Access Panel Installation