INSTALLATION
(1) Using Tool C-4193, install oil pump seal (Fig.
266).
(2) Install transaxle to vehicle (Refer to 21 -
TRANSMISSION/TRANSAXLE/AUTOMATIC - 41TE
- INSTALLATION).
SHIFT INTERLOCK CABLE
REMOVAL
(1) Disconnect the battery negative cable.
(2) Loosen set screw and remove knob from shifter
handle (Fig. 267).
(3) Remove the center console assembly as shown
in (Fig. 268).
(4) Remove shifter bezel (Fig. 269).
(5) Disconnect the shifter/ignition interlock cable
from the shifter lever and bracket as shown in (Fig.
270). Remove the cable core end from the plastic cam
of the shifter mechanism and release cable from
shifter bracket
Fig. 266 Install Oil Pump Seal
1 - TOOL C-4193
2 - HANDLE TOOL C-4171
Fig. 267 Gearshift Knob Removal/Installation
1 - SHIFTER KNOB
2 - SET SCREW
Fig. 268 Center Console Removal/Installation
1 - CONSOLE
2 - SCREW (4)
3 - SCREW (2)