EasyManuals Logo

Keysight Technologies N9030B User Manual

Keysight Technologies N9030B
617 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #552 background imageLoading...
Page #552 background image
552 N9030B PXA Signal Analyzer Service Guide
Post-Repair Procedures
Post-Repair Procedures
Post-Repair Procedures
Table 17-1 lists the adjustments and performance verification tests needed
after an assembly replacement.
After an assembly is replaced, find the assembly that has been replaced in the
left-hand column, and then perform the recommended adjustment and/or
performance verification test. Making the recommended adjustments and/or
performance verification tests doesn’t guarantee all published specifications
are being met. Only a full instrument calibration will do this.
The following procedures are also included in the Additional Tasks” on
page 557.
“Calibration Data Backup and Restore”
“BIOS Settings Verification”
“End User License Agreement (EULA) Acceptance”
“FPGA Synchronization
“Programming Model and Serial Numbers”
Refer to the analyzer user’s guide for information on instrument warm-up
before performing any of the procedures listed in this chapter.

Table of Contents

Other manuals for Keysight Technologies N9030B

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Keysight Technologies N9030B and is the answer not in the manual?

Keysight Technologies N9030B Specifications

General IconGeneral
BrandKeysight Technologies
ModelN9030B
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals